PRG Demoshow Frankfurt 2015

16.04.2015

Auch 2015 begeistert PRG in der Festhalle mit der PRG-Demoshow - Equipmentliste und Video ....


 

 

PRG-Demoshow in der Frankfurter Festhalle, Prolight + Sound 2015
PRG-Demoshow in der Frankfurter Festhalle, Prolight + Sound 2015

 



Auszug aus der Equipment-Liste "Show Area & Festhalle":

Rigging:

  • 79 x hoists CM D8+ 500kg
  • 80 x hoists CM D8 1000kg
  • 24 x hoists Movecat C1 500kg
  • Appro x. 300 running meters Prolyte S52V
  • Appro x.  40 running meters  Prolyte S36V
  • Appro x.  50 running meters  Slick GS
  • All Pre-Riggs equipped with Lifelines

 
Show Lighting:

  • 36 x PRG Bad Boy
  • 12 x PRG Best Boy HP
  • 107 x PRG Best Boy Wash
  • 48 x Icon Beam, available exclusively from PRG
  • 112 x SGM G-Spot
  • 152 x SGM Si x Pack
  • 78 x SGM Q7
  • 48 x SGM P5
  • 35 x SGM P2
  • 36 x SGM Q2
  • 12 x SGM Q7-W
  • 12 x Clay Paky Alphaspot 1500 HPE

 
Entrance Area:

  • 56 x Vari*Lite VL5
  • 25 x Vari*Lite VL1000

 
PRG Products Area:

  • 1 x PRG M-Box Extreme (show)
  • 1 x PRG BadBoy Followspot
  • 2 x PRG BestBoy HP
  • 1 x PRG BestBoy Wash
  • 2 x PRG ReNEW! LED S4 Profile Refit-Kit
  • 1 x PRG Virtuoso 476 Lightingconsole

 

Laser:

  • 8 x RTI FEMTO RGB 6
  • 4 x RTI PIKO RGB 18
  • 2 x RTI PIKO RGB 14 Pure Diode
  • 4 x RTI NANO RGB 20
  • 2 x RTI NANO RGB 30
  • 2 x RTI NANO AT6 RYGCB 35

 
Video:

  • 5 x projections  on C1 decoration objects though 5 x Barco HDQ40 with motion tracking (Media server will be served with the hoist positions and calculates then the resultant picture that needs to be projected)
  • 1 x Centerscreen MC7H - 7,8m  x 4,2m
  • 2 x Sidescreen 4m x 3m (4 x Panasonic PT - DZ13KJ - 12.000lm)
  • 4 x P30 LED Backwall 4m x 8m
  • Chandelier - 460 LED Balls SGM LB-100
  • Entrance projection: 4 x Panasonic PT-DZ21K (20.000lm)
  • 40 Screens (different sizes)
     

Sound:

  • EAW Anya System
  • Beyerdynamik microphones

 
Controle consoles:

  • D3 Media Server
  • MBo x Pro Media Server
  • Nocturne Video Regie
  • 4 x GrandMA 2 Fullsize
  • 2 x GrandMA 2 Light
  • 8 x GrandMA 2 NPU
  • 2 x GrandMA 2 8-Port Node
  • 70 DMX Splitter

 
How and what we move:

  • 21 x trailer material
  • Approx. 200 tons material
  • Approx.  1000m3 material
  • 36 hours installation
  • 930 men days - organization, supervision, installation
  • Approx. 1600 planning hours

 

Video

 